Client note: Progress payments during construction

Read time: 2 minutes

Under most standard building contracts the contractor is paid progressively throughout the project and is required to submit progress claims to the architect on a regular basis. The architect assesses each claim on the basis of work undertaken, the labour and materials used, and any other construction costs in accordance with the construction contract, and then issues a progress certificate which states the amount calculated by the architect to be due and payable to the contractor at the time of issue.

Under this system, your architect is able to protect you from being charged for work not completed, or not in accordance with the requirements of the construction documents.

At the time of letting the building contract, the contractor should be asked to provide a schedule for expected monthly (or other agreed period) progress payments. The actual payments will depend on the amount of work the contractor has completed and will be likely to vary from this schedule. However, a schedule can be a useful guide for your budgeting.

Under most building contracts the architect's responsibility to prepare and issue progress certificates is as an independent professional assessor upon whose assessment and valuation both you and the contractor have agreed to abide. It is one of the few instances under the contract that the architect does not act as your agent and you must not do anything which prevents your architect from carrying out that role of assessor and certifier independently of you.

The following is the usual process and your obligations for progress payments:

  1. The contractor presents a progress claim to the architect.
  2. The architect assesses the claim, determines the monetary amount which the contractor is entitled to under the contract and issues a progress certificate to the contractor.  
  3. The contractor presents the progress certificate and a tax invoice to you for payment.
  4. The building contract usually states a limited time within which you must make the payment. It is important payment is made to the contractor within the time limits otherwise the contractor may claim interest on the outstanding payment amount.
Disclaimer

This content is provided by the Australian Institute of Architects for reference purposes and as general guidance. It does not take into account specific circumstances and should not be relied on in that way. It is not legal, financial, insurance, or other advice and you should seek independent verification or advice before relying on this content in circumstances where loss or damage may result. The Institute endeavours to publish content that is accurate at the time it is published, but does not accept responsibility for content that may or has become inaccurate over time. Using this website and content is subject to the Acumen User Licence.

Was this note helpful?

We are always looking to improve our content and your opinion is important to us. If you have any feedback or suggestions on how this article could be more relevant and useful, please outline below.

Recently Viewed

Performance Solutions
Project
23 August 2023
As-built documentation
Project
24 January 2024
Business continuity and disaster planning
Practice
24 January 2024
Partition system acoustics
Project
30 November 2011
Specialist consultant scope and responsibility
Project
14 June 2023