Managing time during construction

Published: 22 May 2020 | Edited: 20 December 2023

Read time: 8 minutes  To enable an architect to monitor the contractor's performance, the contract documents require the contractor to submit a ...

Project

Float – adjustment of time

Published: 22 May 2020 | Edited: 7 December 2023

Read time: 4 minutes In Construction Industry Terminology (Standen, 2000), float is: the measure of predicted free time in a [program] between ...

Project

Commissioning tenancy works

Published: 22 November 2011

Before practical completion If the work is to be carried out before practical completion of the main building contract (that is, the building ...

Project

The role of the fire safety engineer in the design team

Published: 31 March 2022 | Edited: 20 October 2022

Read time: 4 minutes Since the inception of modern performance-based fire engineering, the fire safety engineer (fire engineer) has become an ...

Project

Performance Solutions in fire engineering

Published: 8 February 2023

Read time: 8 minutes Many of the Deemed-to-Satisfy (DtS) Provisions in the National Construction Code (NCC) are driven by the fire safety objectives ...

Project

AS 4122

Published: 19 April 2017 | Edited: 12 January 2023

Read time: 10 minutes This note covers the two most recent versions of the Australian Standard Consultancy Agreement: AS 4122-2010 and its ...

Project

Client Architect Agreement (CAA2019)

Published: 29 May 2019

Read time: 12 minutes The Institute’s 2019 Client Architect Agreement (CAA2019) can be used for design and building projects of various sizes and ...

Alongside the 2019 Client Architect Agreement (CAA2019) the Institute also publishes the 2019 Client Architect Agreement for Limited Services ( ...

Project

Client Architect Agreement (CAA2024)

Published: 10 October 2024

Read time: 12 minutes The Australian Institute of Architects’ (the Institute) 2024 Client Architect Agreement (CAA2024) can be used for design and ...

Project

Salaries and overheads

Published: 1 December 2015 | Edited: 17 August 2022

Read time: 4 minutes The costs of running an architectural practice consist of fixed and discretionary (controllable) technical and non-technical ...