Australian Standards contracts

Read time: 13 minutes

There are a number of contracts available for use in commercial construction which are published by Standards Australia for building works. The most commonly utilised contracts are AS 2124, AS 4000 and AS 4300. While the contracts appear similar, there are differences between them. The information provided below is general in nature and you should advise your client to seek legal advice to determine the most appropriate form of contract for each specific project.

Page contents:

Common contract types

AS 2124-1992 General conditions of contract

AS 2124 follows a traditional lump sum or fixed-price approach, where the contractor undertakes to complete the project for a predetermined price. It outlines the general conditions of the contract and covers various aspects of the construction project, including scope of work, contract price, time for completion, variations, payments, and dispute resolution. While AS 4000 is intended to supersede AS 2124, the contracts continue to run concurrently. AS 2124 remains a popular contract type that is still widely used and recognizes the importance of design in construction projects.

AS 4000-1997 General conditions of contract

AS 4000-1997 General conditions of contract is based on AS 2124-1992 and is one of the standard contracts in the AS 4000 series. It is also known as AS 4000 Contract. AS 4000, in comparison to AS 2124, allows for greater flexibility in allocating design responsibilities between the owner and the contractor, giving the parties the ability to define specific design obligations in the special conditions of the contract. AS 4000 offers greater flexibility in the way elements of the contract are implemented in comparison to AS 2124. Refer also ‘The main differences between AS 4000-1997 and AS 2124-1992 ’.

Both AS 4000 and AS 2124 contain provisions for staged practical completion, as does ABIC Major Works (MW) 2018, but for other forms of building contract it is necessary for the owner and their legal advisors to prepare such an amendment. Refer Acumen note Staged practical completion.

AS 4300-1995 General conditions of contract for design and construct

AS 4300 is specifically designed for design and construct projects, where the contractor takes responsibility for both the design and construction aspects of the project. The Standard seeks the provision of the Principal’s Project Requirements which form a brief, often including initial design documents and a description of the desired project outcome, for the contractor to follow. While superseded by AS 4902-2000, AS 4300 is still used on many projects.

AS 4902-2000 General conditions of contract for design and construct

AS 4902-2000 General conditions of contract for design and construct is based on AS 4000-1997. AS 4902-2000 introduces similar changes to AS 4300 as AS 4000 does to AS 2124 by providing greater flexibility in allocating responsibilities between the parties.

Back to top

Comparison table

The following table provides a simplified and generic comparison of differences across some items of the contracts.

Aspect AS 2124-1992 AS 4000-1997 AS 4300-1995 AS 4902-2000
Contract structure Fixed-price/lump sum Flexible payment arrangements Flexible payment arrangements Flexible payment arrangements
Design responsibility Contractor-focused design responsibility Flexible allocation of design Flexible allocation of design Flexible allocation of design
Unfixed plant and materials Clear ways for contractor to make claim Not explicitly defined. Additional requirements to be put in place for contractor to make a claim Defines the treatment of unfixed plant and materials Defines the treatment of unfixed plant and materials
Variations Detailed process for handling variations Flexibility in managing variations Specific procedures for variations Superintendent has greater capacity to determine value of variations
Negative Variations     Contractor retains reasonable overheads and profit Contractor retains reasonable profit only
Time extensions Specific provisions for time extensions Flexibility for time extensions. Failure of superintendent to respond deemed approval of EOT Specific provisions for time extensions Flexibility for time extensions similar to AS 4000. Failure of superintendent to respond deemed approval of EOT
Delay damages Addressed in the contract Increased flexibility for what can be claimed under ‘delay damages’ Addressed in the contract Increased flexibility for what can be claimed under ‘delay damages’
Concurrent delays Non-qualifying concurrent delays cancel out qualifying delays Superintendent can apportion delays according to their contribution to a delay Non-qualifying concurrent delays cancel out qualifying delays Superintendent can apportion delays according to their contribution to a delay
Liquidated damages Contractor automatically indebted to the principal Requires superintendent to certify Contractor automatically indebted to the principal Requires superintendent to certify
Notices Greater inclusion of time bars for notices Entitled to claim for breach damages. No specific time bars Specific details included for the issuing of notices for clauses to take effect Notice of delay needs to include estimate of delay (not required in 4300)
Dispute resolution Negotiation, mediation, arbitration Negotiation, mediation, arbitration, litigation option available Negotiation, mediation, arbitration Alternative option for resolution are streamlined

 


Back to top

The main differences between AS 4000-1997 and AS 2124-1992

Note: This section is based on an article in Minter Ellison's On Site newsletter, published with previous permission.

The objectives in drafting AS 4000 were to:

  • make the contract more user-friendly
  • remove ambiguities and inconsistencies
  • remove the administrative detail contained in AS 2124-1992.

AS 2124 continues to be published, as owners, particularly government and semi-government bodies, have been reluctant to change over to AS 4000.

The following section discusses the six main issues in AS 4000 that differ from AS 2124:

  • Extensions of time
  • Progress claims and payment
  • Notification
  • Variations
  • Termination
  • Superintendent’s role

Back to top

Extensions of time (clause 34)

Causes of delay

Under AS 2124, causes of delay entitling the contractor to claim an extension of time (EOT) are listed in clause 35.5.

Under AS 4000 the process is reversed. An EOT can be claimed for a ‘qualifying cause of delay’, which is defined as any act, default or omission of the superintendent, principal or its consultants, agents or other contractors (not being employed by the contractor) other than:

  • a breach or omission by the contractor; and
  • industrial conditions or inclement weather occurring after the date for practical completion.

The principal is required to list in item 23 of the Annexure, all causes of delay that will not entitle the contractor to an EOT. If a cause of delay is not specified in item 23, or is not a breach or omission by the contractor, or does not arise from industrial conditions or inclement weather after the date for practical completion, the contractor will be entitled to claim an EOT.

Other prerequisites for claiming an EOT include:

  • that the contractor is delayed in reaching practical completion
  • that the contractor has taken steps to prevent or mitigate the delay.

Contractors often neglect the procedural requirements necessary to claim an EOT. Consequently, many claims based on a valid cause of delay are rejected. Under AS 4000, a failure to communicate a claim in accordance with the relevant provisions of the contract will not invalidate the claim but may entitle the principal to damages. See clause 41.2.

This is an important change from AS 2124, under which the requirement to submit an EOT claim within 28 days after the delay occurs is a condition precedent to an EOT entitlement.

Procedure for claiming an EOT

a. Notice of delay

Under clause 35.5 of AS 2124, it is necessary to promptly notify the superintendent in writing of details of a possible delay and the cause when it becomes evident:

‘… to the Contractor that anything, including an act or omission of the Principal, the Superintendent or the Principal’s employees, consultants, other contractors or agents, may delay the work under the Contract …’

Under clause 34 of AS 4000, ‘A party becoming aware of anything which will probably cause delay to [work under the Contract] (WUC) ...’ is to ‘… promptly give the Superintendent and the other party written notice of that cause and the estimated delay.’

Unlike AS 2124, AS 4000 makes it clear that it is necessary to provide information regarding the estimated delay.

b. Claim submission

If the contractor is, or will be, delayed in reaching practical completion by a cause described in clause 35.5 of AS 2124, a written claim must be given to the superintendent within 28 days of the delay occurring, setting out the facts on which the claim is based.

Under AS 4000, a contractor is entitled to an extension of time, if the works are or will be delayed in reaching practical completion by a qualifying cause. The contractor shall give the superintendent written notice of the delay, within 28 days of when the contractor should reasonably have become aware of the cause of delay. The notice should include an estimate of the anticipated extent of delay.

Under AS 4000, if further delay results from a qualifying cause, the contractor must promptly give the superintendent a written claim setting out the facts of that delay, in order to claim a further EOT for such delay. Contractors should ensure EOT claims are well documented, addressing each prerequisite for an EOT. Otherwise, principals may be able to reject an EOT claim.

Assessment of an EOT claim

Under AS 2124, the 28-day period in which the superintendent is to respond to an EOT claim is only triggered once the contractor claims a specific period of days as extension of time. If the superintendent fails to respond within 28 days, the contractor's only remedy is to claim damages for breach of contract.

In AS 4000, clause 34.5 provides that, if the superintendent does not assess the contractor’s claim within 28 days of receiving it, the contractor is entitled to the extension of time claimed. This removes the uncertainty that a contractor has in relation to whether or not it will be receiving an extension of time. However, it also makes it more important for contractors to properly document their claims for EOTs.

Delay costs

The events entitling a contractor to claim delay costs are the same. However, the contractor is entitled to ‘delay damages’ rather than ‘its extra cost incurred’. Delay damages may be wider than the actual costs incurred.

Back to top

Progress claims and payment (clause 37 to 39)

The claim

Under AS 2124 a claim has to include:

  • the value of the work carried out by the contractor at the time of making the claim
  • all amounts then due to the contractor arising out of or in connection with the contract or any alleged breach of the contract.

Under AS 4000, the contractor is required to claim payment progressively, in accordance with the requirements set out by the parties in item 28 of the Annexure. The claim only has to include details of the value of the WUC. A contractor may include details of other money then due to the contractor but there is no obligation to provide these details in a progress claim.

Payment of workers and subcontractors

Under clause 38 of AS 4000, the contractor has to provide documentary evidence to the satisfaction of the superintendent of payment of all money in respect of:

  • workers of the contractor and the subcontractor (this only has to be given on request under AS 2124)
  • subcontractors (this is also required as a matter of course under AS 2124).

Unfixed plant and material

Under AS 2124, the principal is obliged to pay for unfixed plant and materials where the item is imported into Australia (provided the contractor gave the principal a clean bill of lading drawn or endorsed to the principal), or where the item is listed in the Annexure to the contract (provided the contractor could establish to the satisfaction of the superintendent that the item had been paid for, is properly stored, labeled and protected).

In relation to all other unfixed plant and materials to be incorporated into the works, AS 2124 provides three alternatives for the parties to choose from:

a. principal not obliged to make payment unless the contractor provides extra security; or 

b. principal not obliged to make payment but may, if the contractor establishes that:

    • the items have reasonably but not prematurely been delivered;
    • ownership will pass to the principal upon payment being made; and
    • the items have been properly stored, labeled and protected; or

c. contractor not entitled to payment. 

AS 4000 is far more restrictive in that it eliminates the options listed in AS 2124. Under AS 4000, the principal is not obliged to make payment for unfixed plant and materials unless they are listed in the Annexure and the contractor provides additional security and satisfies the superintendent that they have been paid for and are properly stored, labeled and protected.

This provision severely limits the contractor's ability to be paid for unfixed goods.

Certification and payment

Under AS 2124, the superintendent has to issue, within 14 days after receipt of a claim for payment, a payment certificate stating the amount of payment (in the opinion of the superintendent) that is to be made by the principal.

Under AS 4000, the superintendent has to, within 14 days after receiving a progress claims, issue the following two certificates:

  • a progress certificate that sets out the superintendent 's opinion of the money due from the principal to the contractor; and
  • a certificate setting out the superintendent's assessment of retention money and money due from the contractor to the principal.

AS 4000 provides that, if the superintendent does not issue the progress certificate within 14 days of receiving a progress claim, the progress claim submitted by the contractor will be deemed to be the relevant progress certificate. This is intended to reduce the incidence of late certification by
superintendents.

Under AS 4000 the principal has seven days, after receipt of both certificates, to pay the contractor the balance of the progress certificate after deducting any retention moneys and setting off any amounts evidenced in the superintendent's second certificate. However, if the superintendent fails to issue the various certificates, the principal must pay the contractor the amount in the progress claim within 21 days after the superintendent receives the progress claim. This is a shorter time limit than under AS 2124 (15 days).

Back to top

Notification (clause 41)

Clause 41 of AS 4000 applies to all claims for which notification is not required under another provision of the contract. It requires a party to notify the other of any claim in connection with the contract as soon as practicable after that party becomes aware of the claim. The notice must be in writing, and:

  • specify the general basis of the claim
  • specify the general quantum of the claim.

Details of the claim are not required for a further 28 days.

This is stricter than under AS 2124, where a party has 28 days after the first day upon which they could reasonably have been aware of a breach to give the notice.

However, a substantial difference under AS 4000 is that if a party fails to notify a claim within the time required, that claim is not barred or invalidated. Unlike AS 2124, AS 4000 also provides a mechanism by which a claim is to be processed:

  • The party giving the notice must give details of the claim within 28 days after it has issued the prescribed notice. If the party fails to give details then the prescribed notice shall be deemed to be the claim.
  • The superintendent then has 56 days, from the receipt of the prescribed notice, to assess the claim and notify the parties of the decision. If neither party disputes that decision, after a further 28 days from notification of the superintendent's decision the superintendent will certify the amount the original decision to be the money that is then due and payable. If a party disputes the decision, they will have to revert to the dispute determination process in clause 42.

Back to top

Variations (clause 36)

Under AS 2124, the superintendent can direct a variation after practical completion in respect of rectification work. This is not possible under AS 4000.

One of the major pitfalls for contractors is the execution of a variation without a written direction to do so. Under clause 36.1 of AS 4000 a contractor is required not to vary WUC except as directed in writing. It is therefore imperative that, before requiring a variation to be executed, the principal/superintendent must issue a written direction. Likewise, before executing a variation a contractor must receive a written direction.

The process for valuing variations has been greatly simplified under AS 4000 and clause 36.4 sets out a clear order of precedence of assessing a variation:

  • prior agreement
  • applicable rates or prices in the contract;
  • rates or prices in a priced bill of quantities, schedule of rates or schedule of prices (even those that are not contract documents) to the extent that it is reasonable to use these documents
  • reasonable rates or prices, which are to include a reasonable amount for profit and overheads.

The clause also makes it clear that any deduction shall include a reasonable amount for profit but not for overheads.

The scope for valuing variations has been greatly expanded by the third option, which allows the superintendent to turn to rates or prices that do not actually form part of the contract documents.

However, they can only be used if it is reasonable to do so and additional protection is provided to contractors by the obligation imposed on the superintendent to fulfill all aspects of the role and functions reasonably and in good faith.

In relation to variations, it is important to note that a number of items that would be assessed as variations under AS 2124 are not valued as such under AS 4000. Rather, the actual cost is assessed by the superintendent and added to or deducted from the contract sum. This will deprive the contractor of the ability to claim overheads and profit on that value.

In addition, the concept of day work is not included in AS 4000.

Back to top

Termination (clause 39)

Under AS 4000, the events entitling a principal to serve a ‘show cause’ notice include a substantial departure from a construction program by the contractor, without reasonable cause. If there is no construction program then the AS 2124 event is used – failing to proceed with due expedition and without delay.

A substantial departure from the construction program will be easier to prove than a failure to proceed with due expedition and without delay.

Back to top

Superintendent's role (clause 20)

Under AS 4000, the principal has to ensure that at all times there is a superintendent, and that the superintendent fulfills all aspects of the role reasonably and in good faith. It is possible these words will make the superintendent more independent than under AS 2124, where the superintendent is required to act ‘honestly and fairly’, although reasonableness is required under AS 2124 for measuring or valuing work, quantities or time.

The intended aim of this clause is to ensure that principals appoint superintendents who act professionally in exercising their duties under the contract.

Back to top

AS member access benefit

Disclaimer

This content is provided by the Australian Institute of Architects for reference purposes and as general guidance. It does not take into account specific circumstances and should not be relied on in that way. It is not legal, financial, insurance, or other advice and you should seek independent verification or advice before relying on this content in circumstances where loss or damage may result. The Institute endeavours to publish content that is accurate at the time it is published but does not accept responsibility for content that may or has become inaccurate over time. Using this website and content is subject to the Acumen User Licence.

Was this note helpful?

We are always looking to improve our content and your opinion is important to us. If you have any feedback or suggestions on how this article could be more relevant and useful, please outline below.

Related Notes

AS 4122
Project
19 April 2017

Recently Viewed

Indigenous cultural authorship and intellectual property
Practice
6 November 2024
Building contract deposits
Project
24 October 2024
2024 Client Architect Agreement (CAA2024)
Project
10 October 2024
Sustainability framework for practice
Environment
12 June 2024
Client note: Project supply chain and labour impacts
Resources
2 May 2024