Certificates

Project
Published: 22 July 2020
Edited: 27 February 2025

Read time: 10 minutes

Under most standard-form building contracts the contractor receives regular payment for the work as it progresses. Progress certificates are issued by the architect in response to a payment claim submitted by the contractor. In all states and territories (except NT and WA), a progress certificate is the same as a payment schedule under the respective Security of Payment Act. In assessing the claim the architect must act independently and not as the agent of the owner.